Balticconnector offshore pipeline construction work in sea completed


(MENAFN- AzerNews) ByTrend

Construction work in the sea for the Balticconnector project offshore pipeline was completed on July 12, 2019,  Trend  reports citing the project's website.

Reportedly, pipe laying was finished at the end of June, and the shielding work was begun in mid-June. 'Now that the shielding work has been finished, all construction work in the sea has been completed. Next, the offshore pipeline will be pressure-tested in July-August, after which the pipeline will be emptied and dried.

'We are satisfied that the construction work for the offshore pipeline has progressed on schedule and that we can begin the final phases of the pipeline according to plan. We are progressing at a good pace towards the end of the year when the pipeline will be commissioned, says Tom Främling, Baltic Connector Oy's Project Director.

The offshore pipeline will be connected to the onshore pipelines in Finland and Estonia during the autumn.

The Balticconnector pipeline will be fully ready at the end of 2019, and gas will start to flow in the pipeline on 1 January 2020 as the Finnish gas market opens.

MENAFN1507201901950000ID1098759643


Legal Disclaimer:
MENAFN provides the information “as is” without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the provider above.