No Feasibility Study Needed For Solar Rooftop Connections Up To 10 Kw In TN


(MENAFN- IANS) Chennai, May 28 (IANS) The Tamil Nadu Electricity Regulatory Commission (TNERC) has directed the state power utility TANGEDCO not to conduct a technical feasibility study for solar rooftop proposals of up to 10 kilowatts.

The regulatory commission in the state in an order dated May 23, has directed the Tamil Nadu Generation and Distribution Corporation (TANGEDCO) to exempt consumers using solar rooftops of up to 10 kilowatt power based on Rule 7(A) of Electricity (Rights of Consumers) Amendment Rules, 2004.

The TNERC came out with the directive after TANGEDCO ordered an exemption on solar rooftops with a capacity of up to only 3 kilowatts.

The directive was required after several households complained that there was a delay in installing rooftop solar systems in households by the TANGEDCO.

The regulatory commission also directed TANGEDCO that the sanction power of the Grid Interactive Solar Photovoltaic Power System capacity of up to 10 kW should be delegated to the lower-level field officers.

While TANGEDCO has to conduct the study and produce the feasibility report for a solar rooftop project in households within a fortnight, consumers told IANS that there has been an inordinate delay.

Meenakshi Sundaram, a retired College professor, who wanted to install a solar rooftop connection of 8 kW, told IANS that there has been a long delay from Tangedco and several consumers like her were dejected.

MENAFN28052024000231011071ID1108263820


IANS

Legal Disclaimer:
MENAFN provides the information “as is” without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the provider above.