(MENAFN- AzerNews)
By Fazlı Sahan
Strenuous efforts are underway at Filyos Port, where the 540
billion cubic meters of gas from the Amasra-1 well in the Sakarya
Gas Field will meet with the land, Yeni Shafak daily has
reported.
At 2,200 meters below sea level, 12 kilometers of equipment are
put between the wells, the report added.
The Natural gas discovery, which was announced on August 21,
2020, as 320 billion cubic meters in the Tuna-1 well in the Sakarya
Gas Field, increased to 405 billion cubic meters on October 17,
2020, with the discovery of 135 billion cubic meters in the
Amasra-1 well, totaling 540 billion cubic meters.
Simultaneously with the discoveries, construction of the
infrastructure that will transport the gas to the land and from
there to the network began. In this backdrop, Turkey had another
historic day in the Black Sea gas production at the start of the
week. The nation witnessed the first pipe lowering and welding
ceremony in the sea.
The Energy and Natural Resources Ministry is working nonstop to
bring this wealth to the country. The ministry works both
underwater and on land at the same time. The installation work at
Filyos Port, where the gas will touch the earth, is reminiscent of
a spider web. Authorities stressed the importance of concurrent
task execution by saying, 'If one starts after the other, this
project will not be completed in 8-10 years'.
According to the officials, the piping work is scheduled to be
completed by the end of 2022. Pipes are laid under the sea in three
lines, rather than one. There is a 16-inch pipeline to carry the
gas and next to it, there is another line where various chemicals
will be sent to the field to assist. From the third line, these
works in the field will be inspected, and the control task will be
carried out. On the other hand, BOTAS is working on another 35-36
kilometer line for connection to the main line in Zonguldak. The
pipes have arrived, their routes have been determined, and the work
continues rapidly.
The wellhead valves are first lowered into the wells to clean
the wellhead. The robots then start cleaning the inside of the
well. The 65-ton valve, which is lowered after the wellhead is
opened, is placed here. This is a very delicate stage since the
width, height, and direction of the valve must be correct from
every angle. After all the tests are completed, the wellhead is
ready for production. There is also a 230-250-ton manifold that is
lowered into the sea together with 3-4 robots.
There is 5,200 personnel working on land and at sea, 1,800 of
whom are involved offshore. The project has encompassed 25 ships as
well as 12-13 helicopters. Personnel and materials are transported
by air. As work nears completion, the number of personnel and
equipment will grow even more. After one month, the number of ships
is expected to rise to 45, with a 1,000-1,500 increase in manpower.
The study includes both foreigners and Turks.16 people from
European and Asian countries, who received Turkish citizenship, are
on the field too.
As in the discovery, the main work is being carried out in the
Black Sea region in delivering the gas to the houses. These
inconspicuous studies are quite interesting. The equipment is
placed at a depth of 2,200 meters. The distance from one end of the
equipment to the other is 12 kilometers. The tasks are all
performed by robots. The works are separated into blocks beneath
the water, with Phase-1 of the first block having completed 66
percent of the work.
---
Follow us on Twitter
@AzerNewsAz
MENAFN16062022000195011045ID1104384461
Legal Disclaimer:
MENAFN provides the information “as is” without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the provider above.