By the end of 2027, it is planned to rebuild 20 passenger
stations on the Absheron peninsula, including the construction of 4
new stations along the corridor in the north-south direction
between Bilajari station and Central Baku station and the
construction of a new station in the territory of Khirdalan city on
the line extending to Sumgayit.
According to Azernews , this was reflected in
the Master Plan for the development of Baku until 2040.
Restoration of the line stretching from Bakikhanov station to
Zira and consisting of 8 stations that will be rebuilt in Bulbula,
Amirjan, Surakhani, Yeni Surakhani, Bina, Gala, Dübandi and Zira,
creation of Garadagh-Guzdak, Zabrat-Mashtagha-Zagulba railway
corridors, as well as Garadag region It is planned to create new
railway stations in the territory and the Khojasan settlement.
In addition to these, the construction of a new railway line to
Heydar Aliyev International Airport, as well as the restoration of
the operation of the Hovsan railway station, are planned to develop
the railway network and increase its role in public transport
coordination.
It is planned to create a new
Binagadi-Mehdiabad-Fatmai-Pirshaghi railway corridor by 2040 to
provide a direct railway connection between the city centre and the
northern direction of the peninsula and to expand the scope of
railway transport.
By 2040, it is planned to increase the total length of the
railway network in Baku from 195.4 km to 338.6 km, and the number
of stations from 26 to 54.
MENAFN08012024000195011045ID1107694907
Legal Disclaimer:
MENAFN provides the information “as is” without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the provider above.