Work on Sangachal terminal expansion project completed by 95%


(MENAFN- Trend News Agency ) Baku, Azerbaijan, Feb. 21

By Maksim Tsurkov – Trend:

Tests of new installations built at the Sangachal terminal within the project of the second stage of the development of Azerbaijan's Shah Deniz biggest gas field have been completed by 95 percent, Rahman Rahmanov, general manager of the Sangachal terminal expansion project within the Shah Deniz Stage 2 project told reporters in Baku Feb. 21.

He added that the construction of all installations completed by 100 percent in 2017.

"Presently, tests are conducted to reveal the leaks,' he said. 'Electrical and other tests of new installations are also carried out. These tests have been completed by 95 percent."

He added that the area of ​​the Sangachal terminal increased by 70 hectares due to the construction of new installations.

"Presently, the area of the terminal is 540 hectares, so it will exceed 600 hectares, which makes the Sangachal terminal one of the biggest ones in the world," Rahmanov said.

Story still developing

MENAFN2102201801870000ID1096492097


Trend News Agency

Legal Disclaimer:
MENAFN provides the information “as is” without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the provider above.