Azerbaijan Rolls Up Sleeves Over Electricity Supply Project In Its Nakhchivan
The existing 110 kV power-transmission infrastructure emanating
from the 110 kV Nakhchivan city substation is slated for an
upgrade, transitioning to cable line technology.
Azerenergy OJSC is in the process of evaluating potential
contractors for the execution of this project.
Concurrently, the organization projected the expenditure to
approximate seven million manat ($4 million).