GE Vernova Blade Failure At UK Site Tied To High Wind Problems


(MENAFN- Live Mint) A blade failure at an offshore wind Farm under construction near the UK occurred in high wind conditions during the commissioning process, according to GE Vernova Inc., the turbine supplier.

The Aug. 22 failure at the Dogger bank project took place while some of the turbine's key systems were disabled because of commissioning work being performed, according to an emailed statement from the company Friday. Commissioning involves work on turbines once they're installed to get them ready to produce electricity.

This was the latest failure by a GE Vernova blade in recent months - the string of incidents have been a public black eye for the company's struggling offshore wind business. Another blade failed at the same Dogger Bank project in May, while a July failure at the Vineyard Wind project in the US led to shards of fiberglass washing ashore and closing beaches in one of the Northeast's most expensive vacation destinations.

“We continue to investigate the recent offshore wind events involving our blades and are taking every necessary step with customers and authorities to safely move forward with the installation of the Dogger Bank and Vineyard Wind farms,” a GE Vernova spokesperson said in the statement.

GE Vernova shares gained 2.5% to trade above $196 at 11:51 a.m. in New York. The shares are up roughly 50% since their debut earlier this year.

The incident this month happened as a major storm approached the region, leading to high winds at the Dogger Bank site off the northeast coast of England. The turbine rotor was locked in position and the yaw system that lets the nacelle turn to face the wind was disabled.

In a statement, Dogger Bank said“the turbine was left in a fixed and static position, rendering it vulnerable during a subsequent storm with high winds,” adding that“GE Vernova analysis has shown that this blade event was not caused by an installation or manufacturing issue.”

The May Dogger Bank incident was because of an installation issue, and the July blade failure has been linked to a manufacturing issue, according to GE Vernova, which said it's taking steps to prevent additional accidents.

With assistance from Cameron Baker and Josh Saul.

This article was generated from an automated news agency feed without modifications to text.

MENAFN30082024007365015876ID1108620686


Live Mint

Legal Disclaimer:
MENAFN provides the information “as is” without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the provider above.