Swiss Energy Provider Profits Harmed By Nuclear Plant Shutdowns
-
Deutsch
de
Axpo macht 2024/25 weniger Umsatz und erleidet Gewinneinbruch
Original
Read more: Axpo macht 2024/25 weniger Umsatz und erleidet Gewinnein
Despite this, Switzerland's largest energy company is reporting a good result.
Total operating performance fell by 3.1% to CHF7.4 billion in the 2024/25 financial year to the end of September. Electricity production fell by around 10% to 32.4 terawatt hours.
+ Could Switzerland build new nuclear power plants?
This was mainly due to planned and unplanned interruptions at the Beznau and Gösgen nuclear power plants as well as a weather-related decline in electricity production from hydropower.
Axpo supplied around 40% of the electricity consumed in Switzerland.
Negative impactThe operating result slumped due to negative effect from shifts in earnings and the development of funds for the decommissioning and disposal of nuclear power plants. EBIT fell by 32% to CHF1.19 billion. The bottom line profit totalled CHF879 million (-42%).
Nevertheless, the board of directors is proposing to shareholders that an ordinary dividend of CHF100 million and an additional special dividend of CHF100 million be paid. Axpo is owned by the cantons and cantonal utilities of north-east Switzerland.
Gösgen lossesLooking to the future, the company is“convinced that it will master the challenges ahead, even in an environment that remains demanding, and that it will utilise the opportunities for further growth that present themselves, particularly in the international business”.
In terms of earnings, the hedged electricity prices would reach their highest level in the 2025/26 financial year.
At the same time, however, the already known delay in the reactivation of the Gösgen nuclear power plant, which is expected to last until February 2026, is likely to have a negative impact on earnings. The nuclear power plant has not been connected to the grid since May 24.
When it published its half-year results, Axpo announced that it expected Gösgen to reduce earnings by CHF150 million to CHF170 million, spread over the two financial years 2024/2025 and 2025/2026.
More More Swiss nuclear plant is off the grid for an indefinite periodThis content was published on Jul 15, 2025 The operator must provide evidence of fallback in case of a possible overload in the feedwater pipework system.
Read more: Swiss nuclear plant is off the grid for an indefinite pTranslated from German by DeepL/mga
Legal Disclaimer:
MENAFN provides the
information “as is” without warranty of any kind. We do not accept
any responsibility or liability for the accuracy, content, images,
videos, licenses, completeness, legality, or reliability of the information
contained in this article. If you have any complaints or copyright
issues related to this article, kindly contact the provider above.

Comments
No comment