Ayodhya Ram Mandir To Be Completed By June 2025, Ramparts By September, Says Construction Committee Chairman


(MENAFN- Live Mint) construction of the Ayodhya Shri RAM Janmabhoomi Temple is set to be completed by June 2025, Construction Committee Chairman Nripendra Mishra told media on December 29.

Mishra announced the completion of construction by June 2025, and said that the rampart and shoe racks will be done by September, with rising tower construction being checked for Aviation safety.

Also Read | bank Holiday on January 1: Are banks open or closed for New Year? Ayodhya Ram Mandir - The Details

“We are committed to completing all construction work by June 2025, except for the ramparts and shoe racks, which are estimated to go on till September 2025. 85 murals will be set up in the museum, of which work on 60 murals has already begun, and 21 murals. including 6 murals of Ram have been completed... New titanium lattices are being made for the Parikrama on the ground, first and second floors,” Mishra stated.

“The biggest challenge is to complete the construction of the rising tower which is also being checked for aviation safety,” he added.

Also Read | Brace for a cold start to 2025: IMD predicts low temperatures in north India Timeline

Speaking to reporters on December 28 too, Mishra had said that they reviewed the construction on Saturday and a timeline for completion of the project would be decided.“The rampart for which approximately 8,40,000 cubic feet of stones are to be laid, only 3 lakh cubic feet is left. Hopefully, will be able to complete the 1 km rampart which has 6 temples by June 2025,” he had said.

Mishra added that Shri Ram Janmabhoomi Temple Construction Committee have requested to name the four gates in the south and north after the respected saints of Ayodhya .

“The final inspection of the statues will be done in Jaipur by the first week of January. Digging has begun for the pool in the middle of the temples inside the complex. Today its design and technical details will be discussed. We have requested our general secretary to name the four gates in the south and north after the respected saints of Ayodhya ,” he further stated.

The 'Pran Pratishtha' ceremony of the temple was held on January 22, 2024, with Prime Minister Narendra Modi performing the Vedic rituals, led by a group of priests.

(With inputs from ANI)

MENAFN29122024007365015876ID1109039025


Live Mint

Legal Disclaimer:
MENAFN provides the information “as is” without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the provider above.