Orezone Reports Q3-2025 Production And Hard Rock Expansion Update
Unit | Q3-2025 | Q2-2025 | Q1-2025 | Nine Months Ended September 30, 2025 | |
Ore processed | Tonnes | 1,523,697 | 1,565,022 | 1,511,303 | 4,600,023 |
Ore grade | Au g/t | 0.55 | 0.62 | 0.67 | 0.61 |
Plant recovery | % | 87.0 | 87.8 | 87.9 | 87.6 |
Gold produced | Au oz | 23,371 | 27,548 | 28,688 | 79,607 |
Hard Rock Plant Expansion Overview
The 2.5Mtpa stage 1 hard rock expansion is designed to process higher-grade hard rock ore. The expansion is independent of the adjacent 6.0Mtpa oxide plant but will utilize a number of shared services and infrastructure including the tailings storage facility, warehouses, administration complex, and technical services. The concentrated scope of the brownfield expansion significantly reduces schedule and budget risk in comparison to a new build, with the ramp-up to benefit from the well-established mining, processing, and maintenance teams onsite.
Stage 1 expansion is scheduled for commissioning in November. As with the oxide plant, which had a nameplate capacity of 5.2Mtpa, the Company anticipates significantly better throughput rates than that of the 2.5Mtpa stage 1 design.
The subsequent stage 2 expansion, which will increase the hard rock nameplate throughput to 5.5Mtpa, is forecasted to increase the overall production profile to 225,000-250,000 ounces per year2. With a 5.5Mtpa jaw crusher currently being installed in stage 1, the stage 2 expansion will primarily consist of a ball mill, pebble crusher, thickener, four additional CIL tanks and a gold room upgrade. The stage 1 plant layout was designed to accommodate these stage 2 additions.
Figure 1: Stage 1 Hard Rock Expansion – Major Plant Components, Equipment & Infrastructure
About Orezone Gold Corporation
Orezone Gold Corporation (TSX: ORE | ASX: ORE | OTCQX: ORZCF) is a West African gold producer engaged in mining, developing, and exploring the Bomboré Gold Mine in Burkina Faso. Construction of the stage 1 hard rock expansion is nearing completion, with first gold expected in Q4-2025. Combined production from the oxide and stage 1 hard rock operations is forecasted to total between 170,000 and 185,000 ounces in 2026. The Company is also advancing stage 2 of the hard rock expansion, which is forecasted to increase annual production to between 220,000 and 250,000 ounces.
Contact Information
Patrick Downey
President and Chief Executive Officer
Kevin MacKenzie
Vice President, Corporate Development and Investor Relations
Tel: 1 778 945 8977
... /
For further information please contact Orezone at +1 (778) 945-8977 or visit the Company's website at .
The Toronto Stock Exchange neither approves nor disapproves the information contained in this news release.
This announcement was authorized for release by Patrick Downey, Director, President & CEO.
Qualified Persons and Competent Person Statement
The scientific and technical information in this news release was reviewed and approved by Mr. Rob Henderson, P. Eng, Vice-President of Technical Services and Mr. Dale Tweed, P. Eng., Vice-President of Engineering, both of whom are Qualified Persons as defined under NI 43-101 - Standards of Disclosure for Mineral Projects and Competent Persons as defined under the JORC Code (2012 Edition). Each of Messrs. Henderson and Tweed have sufficient experience that is relevant to the scientific and technical information disclosed in this news release and to the type of activity undertaken to qualify as Competent Persons as defined in the JORC Code. Both are employees of the Company and have consented to the inclusion in this announcement of all technical information based on their work the form and context in which it appears.
Cautionary Note Regarding Forward-Looking Statements
This press release contains certain information that may constitute“forward-looking information” within the meaning of applicable Canadian Securities laws and“forward-looking statements” within the meaning of applicable U.S. securities laws (together,“forward-looking statements”). Forward-looking statements are frequently characterized by words such as“plan”,“expect”,“project”,“intend”,“believe”,“anticipate”,“estimate”,“potential”,“possible” and other similar words, or statements that certain events or conditions“may”,“will”,“could”, or“should” occur. Forward-looking statements in this press release include, but are not limited to, statements that Orezone is well positioned to achieve its 2025 production guidance of 115,000-130,000 ounces, the construction of the stage 1 hard rock expansion is well advanced with completion, commissioning and first gold set for Q4-2025 and once commissioned, will increase annual production by approximately 45%, the potential greater capacity than the 2.5Mtpa design of the stage 1 hard rock plant, and statements with respect to the stage 2 hard rock expansion including the forecast to increase the overall production profile of 225,000-250,000 ounces per year.
All such forward-looking statements are based on certain assumptions and analyses made by management in light of their experience and perception of historical trends, current conditions and expected future developments, as well as other factors management and the qualified persons believe are appropriate in the circumstances.
All forward-looking statements are subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those projected in the forward-looking statements including, but not limited to, delays caused by pandemics, terrorist or other violent attacks (including cyber security attacks), the failure of parties to contracts to honour contractual commitments, unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; social or labour unrest; changes in commodity prices; unexpected failure or inadequacy of infrastructure, the possibility of unanticipated costs and expenses, accidents and equipment breakdowns, political risk, unanticipated changes in key management personnel and general economic, market or business conditions, the failure of exploration programs, including drilling programs, to deliver anticipated results and the failure of ongoing and uncertainties relating to the availability and costs of financing needed in the future, and other factors described in the Company's most recent annual information form, management discussion and analysis and Section 4 of the ASX Prospectus dated July 11, 2025 filed on SEDAR+. Readers are cautioned not to place undue reliance on forward-looking statements.
Although the forward-looking statements contained in this press release are based upon what management of the Company believes are reasonable assumptions, the Company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this press release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the Company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this press release.
______________________________
1 Refer to the Company's ASX Prospectus dated July 11, 2025, a copy of which is available on the Company's website. The Company confirms it is not aware of any new information or data that materially affects the information included in the Prospectus and that all material assumptions and technical parameters underpinning the forecast gold production targets in the Prospectus continue to apply and have not materially changed.
2 Refer to footnote 1.
A photo accompanying this announcement is available at

Legal Disclaimer:
MENAFN provides the
information “as is” without warranty of any kind. We do not accept
any responsibility or liability for the accuracy, content, images,
videos, licenses, completeness, legality, or reliability of the information
contained in this article. If you have any complaints or copyright
issues related to this article, kindly contact the provider above.
Most popular stories
Market Research

- Crypto Market Update: Pepeto Advances Presale With Staking Rewards And Live Exchange Demo
- Tria Raises $12M To Be The Leading Self-Custodial Neobank And Payments Infrastructure For Humans And AI.
- Simplefx Relaunches First Deposit Bonus
- Chartis Research And Metrika Release Comprehensive Framework For Managing Digital Asset Risk
- Whale.Io Launches Battlepass Season 3, Featuring $77,000 In Crypto Casino Rewards
- M2 Capital Announces $21 Million Investment In AVAX Digital Asset Treasury, AVAX One
Comments
No comment