According to the source, electrical facilities are restored inthe highlands with year-round snow.
The laying of 35 kV power transmission lines is rapidly underwayin the district.
Reconstruction work has been completed in the direction ofIstisu, Zod, Zar, Zaylik, and Yellija villages.
Work continues to update the electrical grid; new metal supportsare installed, and modern insulated cable lines are laid in thedirection of Aghgaya, Gamishli, and Marjimak villages.
As part of the reconstruction, construction of a 110/35 kVsubstation continues in Istisu village, as does the laying of anoverhead line with a voltage of 110 kV from Kalbajar city (theKalbajar substation with a capacity of 110/35/10 kV) to Istisu.
Moreover, the construction of a new substation with a capacityof 35/0.4 kV and a digital control center has been completed inKalbajar city.
As a result of the work carried out, a ring power supply schemewill be created connecting the power grids of Kalbajar and Lachindistricts.
To note, Azerishig OJSC is concurrently progressing with thereconstruction of power grid facilities across all regions of thecountry.
Stay up-to-date with more news on Trend News Agency'sWhatsApp channel

Legal Disclaimer:
MENAFN provides the information “as is” without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the provider above.