Azerbaijan Tracks Reconstruction Progress For Alat-Osmanli-Astara Railway Line
It was noted that the total length of the railway line along the axis is 245 kilometers, and the construction work is planned to be completed in 2027.
"As many as 55% of the design work has been completed. Besides, 56% of the construction and installation work on the Alat-Osmanli section of the line has been completed.
The project is being implemented in four stages. The first stage covers the 60-kilometer-long Alat-Osmanli section. The construction of a new railway bridge over the Kura River has been completed within the framework of the second stage.
--