Azerbaijan's Azvirt LLC Conducting Excavation Work At Under-Construction Lachin Airport (Exclusive)


(MENAFN- Trend News Agency)

BAKU, Azerbaijan, October 19. Excavation work at the under-construction airport in Azerbaijan's Lachin is currently underway, media Manager of AzVirt LLC Jeyhun Safarov told at the Baku expo Center on October 19.

According to him, the relevant work takes a long time due to the difficult terrain.

'We believe current excavations will be completed by the end of 2024 – beginning of 2025. AzVirt LLC is making every effort to have all work done on time,' Safarov said.

As he noted, the company is engaged in the construction of three major areas of the airport.

'These areas are airport runways, aprons, and guideways,' Safarov said.

Lachin Airport is the third to be built on Azerbaijan's liberated lands. The grand opening of Fuzuli Airport took place on October 26, 2021, while the opening of Zangilan Airport is expected to be held on October 20, 2022.

MENAFN19102022000187011040ID1105047417


Trend News Agency

Legal Disclaimer:
MENAFN provides the information “as is” without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the provider above.