Cornish Metals Completes An Updated PEA Of The South Crofty Critical Mineral Project With An NPV Of £180 Million And 20% IRR
Summary Operating & Financial Metrics | ||
Operations | Mine throughput | 500 ktpa |
Processed throughput (post pre-concentration) | 250 ktpa | |
LOM | 14 years | |
Total LOM tonnes mined | 5,938 kt | |
Average mined tin grade | 0.94% | |
Contained tin | 55,982 t | |
Total LOM concentrator tonnes processed | 2,874 kt | |
Average processed tin grade | 1.89% | |
Average tin recovery | 87.8% | |
Total LOM tin produced | 49,168t | |
Total LOM copper produced | 3,842 t | |
Total LOM zinc produced | 3,223 t | |
Years 2–6 average annual tin production | 4,695 t | |
Capital costs | Pre-production | £198 million |
Post-production sustaining | £43 million | |
Operating costs | Average net cash cost in years 2–6 | US$12,302 /tonne tin payable |
Average LOM net cash cost | US$13,494 /tonne tin payable | |
Average AISC in years 2–6 | US$13,419 /tonne tin payable | |
Average LOM AISC | US$14,461 /tonne tin payable | |
Economic assumptions | Tin price | US$33,900 /tonne |
GB£:US$ | 1.30 | |
UK corporate tax rate | 25% | |
Financials | NPV (6% Real) – Pre-tax / After-tax | £237 million / £180 million |
IRR – Pre-tax / After-tax | 23% / 20% | |
Capital payback period after-tax | 3.3 years | |
Total LOM net Revenue | £1.2 billion | |
Total LOM EBITDA | £693 million | |
After-tax Free Cash Flow (from start of production) | £558 million | |
Years 2–6 average annual after-tax Free Cash Flow | £57 million | |
Years 2–6 average annual EBITDA / EBITDA margin | £70 million / 62% |
Table 1: South Crofty operating and economic summary
Notes:
- NPV effective as at 1 April 2026; Mine plan and financial modelling include Inferred Mineral Resources.
The evaluation at this level of study includes Indicated and Inferred blocks and consequently it is not possible to define a Mineral Reserve. This study is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have economic considerations applied that would enable them to be categorised as Mineral Reserves. There is no certainty that this study will be realised.
Capital and Operating Costs
The pre-production capital cost of the South Crofty project commencing from 1 April 2026 is estimated to be £198 million. The LOM sustaining capital is estimated to be a further £43 million, comprising mainly underground development and a process plant upgrade to treat polymetallic material.
(£ million) | % | |
Mine development and pre-production | 48.8 | 25% |
Process plant | 51.7 | 26% |
Site development and ancillary facilities | 4.0 | 2% |
Other surface infrastructure | 7.4 | 4% |
Tailings management | 10.0 | 5% |
Owners cost | 39.2 | 20% |
Indirects | 19.9 | 10% |
Contingency | 17.3 | 9% |
Total pre-production capital | 198.3 | 100 % |
Table 2: South Crofty pre-production capital costs (1 April 2026)
The pre-production capital estimate increased from the 2024 PEA estimate of £142 million reflecting, among other things, changes to scope, labour costs, longer mine dewatering and shaft refurbishment costs, extended timeline and general cost escalation.
The South Crofty underground mining operation is estimated to have a low total unit operating cost, averaging approximately £85 per tonne of mineralised material, totalling approximately £520 million over the 14-year LOM.
Unit Cost (£/t) | Total LOM Cost (£ million) | % | |
Mining & hoisting | 52.6 | 313.4 | 60% |
Processing | 16.0 | 95.5 | 18% |
Pumping and water treatment | 6.4 | 38.2 | 7% |
G&A, including closure cost | 12.5 | 74.2 | 14% |
Total | 87.5 | 521.3 | 100 % |
Table 3: South Crofty operating costs
Average LOM net unit cash costs, inclusive of treatment charges and by-product credits from copper and zinc are estimated to be US$13,494 per tonne of payable tin sold. The LOM AISC is estimated at US$14,461 per tonne. Over the first full five years of production the net cash cost and AISC are estimated at US$12,302 per tonne and US$13,419 per tonne, respectively, potentially positioning South Crofty within the first quartile of the global tin industry cost curve.
Figure 1: South Crofty expected to be a lowest quartile cost tin producer (2030 net cash cost of production). Source: International Tin Association
Cash Flow Generation
South Crofty's estimated low operating costs and a well-supported tin price environment are expected to translate to high margin tin sales and strong cash generation. After-tax free cash flow is estimated to total approximately £357 million across the Project (£558 million from start of production), averaging approximately £57 million in years two through six and peaking at £67 million in the third year of production. The Company hopes to replicate this in later years through planned exploration programmes and extended mine production plans.
Figure 2: South Crofty after-tax free cash flow profile
Sensitivity Analysis
South Crofty project economics are well supported at a range of tin price assumptions and discount rates.
After-tax NPV (£ million) | Commodity Price | ||||||
-20% | -10% | 0 % | +10% | +20% | |||
Discount Rate (Real) | 5 % | 71 | 138 | 204 | 269 | 335 | |
6 % | 57 | 119 | 180 | 242 | 304 | ||
7 % | 43 | 101 | 160 | 218 | 276 | ||
8 % | 31 | 86 | 140 | 195 | 250 | ||
9 % | 19 | 71 | 123 | 174 | 226 |
Table 4: Metal price and discount rate sensitivity analysis
The base-case tin price of US$33,900 /tonne, based on Project Blue's latest price forecast from the Q3 2025 Medium-Term Outlook analysis published in July 2025, reflects a tin market environment of supply falling short of demand in the medium-term that will drive the market into a deficit. The spot tin price, recently trading at approximately US$35,000 /tonne, above our assumption, at which level the estimated NPV6% would increase by approximately £20 million to approximately £200 million. A sensitivity analysis was performed on the study's pre-tax NPV to examine project sensitivity to metal prices, capital and operating costs, grades and process recoveries.
Figure 3: Pre-tax NPV6% sensitivity analysis to various project parameters
Production Profile
South Crofty's production profile is based on an annual mined throughput of approximately 500,000 tonnes and annual processing of approximately 250,000 tonnes following pre-concentration at an average tin grade of 1.89%. Tin in concentrate production over a 14-year LOM is expected to total slightly more than 49,000 tonnes, averaging approximately 4,700 tonnes of tin in concentrate per year in the first five years post ramp-up (years two through six) (see blue box in Figure 4).
Figure 4: South Crofty indicative production profile
The use of pre-concentration employing the latest X-Ray Transmission ("XRT") ore sorting technologies reduces the volume of material processed and required for backfilling to approximately half of the material mined. The impact to concentrator feed grades is also significant, with LOM processed tin grades averaging 1.89%, approximately double the average mined grade of 0.94% tin. Estimated processed tin grades in years two through six average approximately 2.1%.
Figure 5: South Crofty mined and processed tin grades
Indicative timeline
The pace of activities at South Crofty continues to rise as the newly reinforced leadership team works towards first tin production by mid-2028. Key areas of focus and deliverables are outlined in the indicative timeline below:
Figure 6: Indicative timeline to first tin production
Opportunities
This study is constrained by the current South Crofty Mineral Resource Estimate updated in September 2023 that produced a significant increase in contained tin in the Indicated category of the lower mine. Additional in-mine exploration provides the opportunity to extend South Crofty's mine life well beyond the current constrained 14-year LOM. Near-mine exploration targets, such as the Wide Formation, provide further potential to add to the existing Mineral Resource base.
Historic production at South Crofty demonstrates consistent discovery of new material and subsequent conversion to Reserves (Figure 7).
Figure 7: South Crofty cumulative metal mined and metal added to Reserve – 1974 to 1997.
In November 2024, Cornish Metals produced a near mine Exploration Target1 that points to potential additional mineralisation of 6Mt to 13Mt, at a tin grade of 0.5% to 1.8%. The Company plans to test the Exploration Target systematically alongside underground development and production at South Crofty , with the purpose of definition of additional supplementary mineralisation. This is expected to be carried out through targeted drilling programmes aimed at extending the existing Mineral Resource both along strike and down dip, particularly during the early years of operation.
The Company has developed a resource drilling programme that, subject to funding, is planned to commence with the start of underground development and continue alongside production. The South Crofty mine benefits from being a brownfield operation through access to over 25 years of digitalised exploration, development and production data. The programme will be focused on resource definition and expansion with the aim of replacing mined resources, continuing the resource replacement trend demonstrated through the mine's production history.
The near mine exploration target demonstrates the potential to maintain a stable and higher rate of production beyond the sixth year of production, as well as an extended mine life well in excess of the study's constrained 14 years. The Company is also assessing the potential for increased throughput, with further growth opportunities from longer term exploration activities within Cornish Metals' wider mineral rights holdings in Cornwall.
The Study's production profile for South Crofty indicates total tin production of slightly above 49,000 tonnes over a 14-year mine life, averaging approximately 4,700 tonnes of tin per year in the first five years post ramp-up (years two to six) with a declining trend in later years. The production profile is constrained by the current South Crofty Mineral Resource as last updated in September 2023.
The near mine Exploration Target points to potential additional mineralisation at South Crofty and it is management's belief that the production profile in years two through six might be prolonged if the Company replicates its historical record of consistently replacing mined tonnes to extend its life of mine. The Company is also assessing the potential for increased throughput, with further growth opportunities from longer term exploration activities within Cornish Metals' wider mineral rights holdings in Cornwall.
Figure 8: South Crofty tin production profile.
Qualified Persons
The Qualified Persons for the updated PEA are Mr Dominic Claridge, FAusIMM, Principal Mining Engineer (AMC); Mr Nick Szebor, MCSM, CGeol, EurGeol, FGS, Director/Global Lead - Geosciences and Principal Geologist (AMC); Mr Mike Hallewell, FIMMM, FSAIMM, FMES, CEng (Independent Consultant); Mr Barry Balding, PGeo, EurGeol, Technical Director – Mining Advisory Europe (SLR); Mr Steve Wilson, ACSM, CEng, FIMMM, Managing Director: Europe (P&C). Qualified Persons under National Instrument 43-101 (NI 43-101) and Competent Persons as defined under the JORC Code (2012).
All QPs have reviewed the technical content of this news release for the South Crofty deposit and have approved its dissemination.
A Technical Report disclosing the updated PEA in accordance with the requirements of NI 43-101 will be prepared by AMC on behalf of Cornish Metals and filed on SEDAR within 45 days of this news release. Messrs Claridge, Szebor, Hallewell, Balding, Wilson and O'Connell, and Ms Collins consent to the inclusion in this announcement of the matters based on their information in the form and context in which it appears.
This news release has been reviewed and approved by Mr Stephen Holley, (BSc (Hons), ACSM, MSc, MSCM, CEng FIMMM), Technical Services Manager for Cornish Metals Inc, who is the designated QP for the Company.
ABOUT CORNISH METALS
Cornish Metals is a dual-listed mineral exploration and development company (AIM and TSX-V: CUSN) that is advancing the South Crofty tin project towards production. South Crofty:
- is a historical, high-grade, underground tin mine located in Cornwall, United Kingdom and benefits from existing mine infrastructure including multiple shafts that can be used for future operations; is permitted to commence underground mining (valid to 2071), construct a new processing facility and for all necessary site infrastructure; would be the only primary producer of tin in Europe or North America. Tin is a Critical Mineral as defined by the UK, American, and Canadian governments as it is used in almost all electronic devices and electrical infrastructure. Approximately two-thirds of the tin mined today comes from China, Myanmar and Indonesia; benefits from strong local community, regional and national government support with a growing team of skilled people, local to Cornwall, and could generate over 300 direct jobs.
ON BEHALF OF THE BOARD OF DIRECTORS
“Don Turvey”
Don Turvey
CEO and Director
Engage with us directly at our investor hub. Sign up at:
For additional information please contact:
Cornish Metals | Fawzi Hanano Irene Dorsman | ... ... |
Tel: +1 (604) 200 6664 | ||
SP Angel Corporate Finance LLP (Nominated Adviser & Joint Broker) | Richard Morrison Charlie Bouverat Grant Barker | Tel: +44 203 470 0470 |
Hannam & Partners (Joint Broker) | Matthew Hasson Andrew Chubb Jay Ashfield | ...ners Tel: +44 207 907 8500 |
BlytheRay (Financial PR) | Tim Blythe Megan Ray Said Izagaren | ... Tel: +44 207 138 3204 |
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Caution regarding forward looking statements
This news release may contain certain“forward-looking information” and“forward-looking statements” (collectively,“forward-looking statements”). Forward-looking statements include predictions, projections, outlook, guidance, estimates and forecasts and other statements regarding future plans, the realisation, cost, timing and extent of mineral resource or mineral reserve estimates, estimation of commodity prices, currency exchange rate fluctuations, estimated future exploration expenditures, costs and timing of the development of new deposits, success of exploration activities, permitting time lines, requirements for additional capital and the Company's ability to obtain financing when required and on terms acceptable to the Company, future or estimated mine life and other activities or achievements of Cornish Metals. Forward-looking statements are often, but not always, identified by the use of words such as“seek”,“anticipate”,“believe”,“plan”,“estimate”,“forecast”,“expect”,“potential”,“project”,“target”,“schedule”,“budget” and“intend” and statements that an event or result“may”,“will”,“should”,“could”,“would” or“might” occur or be achieved and other similar expressions and includes the negatives thereof. All statements other than statements of historical fact included in this news release, are forward-looking statements that involve various risks and uncertainties and there can be no assurance that such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements.
Forward-looking statements are subject to risks and uncertainties that may cause actual results to be materially different from those expressed or implied by such forward-looking statements, including but not limited to: risks related to receipt of regulatory approvals, risks related to general economic and market conditions; risks related to the availability of financing; the timing and content of upcoming work programmes; actual results of proposed exploration activities; possible variations in Mineral Resources or grade; projected dates to commence mining operations; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes, title disputes, claims and limitations on insurance coverage and other risks of the mining industry; changes in national and local government regulation of mining operations, tax rules and regulations. The list is not exhaustive of the factors that may affect Cornish's forward-looking statements.
Cornish Metals' forward-looking statements are based on the opinions and estimates of management and reflect their current expectations regarding future events and operating performance and speak only as of the date such statements are made. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ from those described in forward- looking statements, there may be other factors that cause such actions, events or results to differ materially from those anticipated. There can be no assurance that forward-looking statements will prove to be accurate and accordingly readers are cautioned not to place undue reliance on forward-looking statements. Cornish Metals does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations or opinions should change other than as required by applicable law.
Market Abuse Regulation (MAR) Disclosure
The information contained within this announcement is deemed by the Company to constitute inside information pursuant to Article 7 of EU Regulation 596/2014 as it forms part of UK domestic law by virtue of the European Union (Withdrawal) Act 2018 as amended.
Appendix 1 – South Crofty summary LOM operating and financial model
1 The potential quantity and average grade of the near mine Exploration Target is conceptual in nature and is an approximation. There is insufficient data to estimate a Mineral Resource in the area considered and it is uncertain if further exploration will result in the definition of a Mineral Resource.
Photos accompanying this announcement are available at

Legal Disclaimer:
MENAFN provides the
information “as is” without warranty of any kind. We do not accept
any responsibility or liability for the accuracy, content, images,
videos, licenses, completeness, legality, or reliability of the information
contained in this article. If you have any complaints or copyright
issues related to this article, kindly contact the provider above.
Most popular stories
Market Research

- Seoul Exchange, One Of Only Two Licensed Platforms For Unlisted Securities, Will Exclusively Use Story To Settle Tokenized Rwas
- Phase 6 Reaches 50% Mark As Mutuum Finance (MUTM) Approaches Next Price Step
- 0G Labs Launches Aristotle Mainnet With Largest Day-One Ecosystem For Decentralized AI
- Solotto Launches As Solana's First-Ever Community-Powered On-Chain Lottery
- Kintsu Launches Shype On Hyperliquid
- Blockchainfx Raises $7.24M In Presale As First Multi-Asset Super App Connecting Crypto, Stocks, And Forex Goes Live In Beta
Comments
No comment