Azerbaijan's Nakhchivan SPP Hits New Milestones In Energy Production (Exclusive)
Date
1/12/2025 12:06:22 AM
(MENAFN- Trend News Agency)
BAKU, Azerbaijan, January 12. The solar power
plant (SPP) in Azerbaijan's Nakhchivan Autonomous Republic produced
over 32,000 kilowatt-hours of electricity in 2024, the Nakhchivan
State energy Service told Trend .
In an exclusive statement to the agency, the service noted that
the SPP is expected to produce a total of 33 million kilowatt-hours
of electricity by the end of the year.
To note, the construction and installation work for the SPP,
located in the Babek district, was carried out under an agreement
signed on February 7, 2015, between the Nakhchivan Autonomous
Republic's State Energy Service and the Belgian Royal Company,
Soltech. Initially, the plant's capacity was set at 20 megawatts,
and after successful completion, it became operational on November
30, 2015. The plant's capacity was later expanded by an additional
2 megawatts in September 2017, reaching 22 megawatts.
Nakhchivan's favorable geographic location and climate
conditions make it an ideal region for harnessing clean, renewable
solar energy. The region enjoys an average of 2600-2800 sunshine
hours per year, which ensures that the solar power plant plays a
crucial role in the energy security of Nakhchivan. The solar energy
intensity in the region is between 0.8-1.2 kilowatt-hours per
square meter.
MENAFN12012025000187011040ID1109080179
Legal Disclaimer:
MENAFN provides the information “as is” without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the provider above.