Abcourt Presents Operations Update For February 2026 In The Development Of The Sleeping Giant Mine And A Corporate Update
| Q1 2025/09/30 | Q2 2025/12/31 | Q3 2026/03/31 to date | January | February | YTD | |
| Diamond Drilling (m) | 6,467 | 4,572 | 4,120 | 1,537 | 2,583 | 15,159 |
| Underground Rehabilitation (m) | 1,703 | 903 | 143 | 127 | 17 | 2,749 |
| Underground Development (m) | 71 | 290 | 169 | 84 | 85 | 530 |
| Tonnes Milled (tonnes) | 3,511 | 5,652 | 4,562 | 2,759 | 1,803 | 13,725 |
| Mill Head Grade (g/t) | 5.9 | 6.2 | 6.6 | 7.3 | 5.7 | 6.3 |
| Ounces Milled (oz) | 664 | 1,125 | 972 | 644 | 328 | 2,761 |
| % Recovered | 94.9% | 96.1% | 97.1% | 97.2% | 97.0% | 96.2% |
| Ounces Produced (oz) | 630 | 1,081 | 944 | 626 | 318 | 2,655 |
| Ounces Poured (oz) | 26 | 837 | 772 | 374 | 398 | 1,635 |
The gold inventory in the circuit at the end of the month of February was 1,020 ounces.
Work at the camp continued in February with the addition of a 36-room block, on top of the existing 50 rooms. This second phase of adding rooms is expected to be completed in the coming weeks. Construction of the third block of rooms is scheduled to begin in early summer.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Photos accompanying this announcement are available at
Legal Disclaimer:
MENAFN provides the
information “as is” without warranty of any kind. We do not accept
any responsibility or liability for the accuracy, content, images,
videos, licenses, completeness, legality, or reliability of the information
contained in this article. If you have any complaints or copyright
issues related to this article, kindly contact the provider above.


Comments
No comment