Dhaka: The expansion and modernisation works of all eight airports in the country, both international and domestic, worth BDT 350 billion, will finish by the end of 2023, said Air Vice Marshal M Mafidur Rahman, Chairman of Civil Aviation Authority of Bangladesh.

“Once the work is completed, there will be major changes in the infrastructures of all the country's airports. All the eight airports will be equipped with modern amenities and attractive look,” added the CAAB chief.


“Over 70 per cent of work of the Third Terminal of Hazrat Shahjalal International Airport in Dhaka has been completed and the operational activities of the new terminal will be inaugurated in October, 2023 by Prime Minister Sheikh Hasina,” he mentioned.

“After completion of the Third Terminal, passenger handling capacity at Dhaka airport will increase from 10 million to 22 million. Besides, cargo handling capacity will rise from 0.22 million tonnes to 0.70 million tonnes,” added CAAB Chairman.

Also, construction work on the 73,548 square meter cargo apron of the airport is now underway. 85 per cent of the project has been completed and after implementation, the apron will be able to park additional four long-range cargo aircraft.

Besides, the construction of a general aviation hangar, hangar apron and fire station expansion project at Dhaka airport, at a cost of BDT 4.30 billion, is ongoing.

This project includes the construction of a 23,589 square meter general aviation hangar, 65,068 square meter hangar apron, 29,988 square meters new parking area and a 5-storey building with 5,000 square meter floor space. 65 per cent of the work has been done so far.

Construction work for the country's first-ever heliport, a dedicated landing facility for helicopters, is also underway. The main objective of this project is to ensure the safe take-off and landing of helicopters.

Under the existing runway and taxiway power enhancement project of Sylhet's Osmani Airport, the power of the runway and taxiway is being increased from 41 PCN (pavement classification number) to 90 PCN at a cost of BDT 4.51 billion, project authorities said.

99 per cent of the work has been completed. When it will fully complete, Boeing-777 aircraft will be able to land at this airport at full speed, they said.

According to the project source, the length of Cox's Bazar airport runway has been increased to 9,000 feet from 6,775 feet under the development project.

The runway of Barishal airport is also being increased from 6,000 to 7500 feet at a cost of BDT 3.70 billion. The width of the runway is being increased from 100 to 150 feet, project authorities said.

30 per cent work of runway and taxiway capacity enhancement and expansion of Shah Amanat International Airport in Chattogram has been completed. Once implemented, Boeing 777 aircraft will be able to take off and land on the runway.

The terminal building of Saidpur Airport is being turned into an international standard one. The project is near to completion.

Once implemented, the accommodation capacity of the building will increase from 310 to 670 people. Besides, a new passenger terminal building, cargo building with automation, and operational building with an apron, taxiway, and control tower will be constructed for this airport.

Rajshahi Terminal Building Expansion Project is going on at a cost of BDT 760 million. The project includes the construction of the terminal building, the installation of an electro-mechanical and control tower along with communication and security equipment. This will increase the passenger accommodation capacity of the current terminal from 260 to 850.

The Jashore Terminal Building Expansion Project will increase passenger accommodation capacity from 300 to 600 people. 99 per cent work of the project has been completed.

Apart from this, another project has been undertaken to ease the take-off and landing of aircraft at Jashore, Saidpur, and Rajshahi airports at a cost of BDT 5.66 billion.

  • T

MENAFN01022023000163011034ID1105507900


Legal Disclaimer:
MENAFN provides the information “as is” without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the provider above.