Egypt Starts Mina West Gas Output, Adding 160 MMcf/d Supply
(MENAFN) Egypt has brought the offshore Mina West gas field online, opening a fresh source of domestic supply that is expected to deliver as much as 160 million standard cubic feet per day.
Shell Egypt and Kuwait Foreign Petroleum Exploration Company (KUFPEC) said Sunday that output began just three years after the discovery.
The field sits within the North East El Amriya concession in the Mediterranean Sea. Shell controls 60% of the project, and KUFPEC’s Egyptian subsidiary holds the other 40%.
The partners signed off on development in June 2025. A newly built seven-kilometer (4.34-mile) pipeline ties the field into the existing West Delta Deep Marine infrastructure, which sends the gas to the Burullus processing facility before it reaches Egypt’s national grid. Shell said relying on existing facilities sped up the timeline.
“Bringing Mina West into production just three years after discovery demonstrates what we can achieve when we work towards a shared goal from the outset,” said Dalia Elgabry, Shell Egypt’s vice president and country chair.
Elgabry attributed the fast turnaround to early coordination among Egypt’s Petroleum Ministry, the Egyptian Natural Gas Holding Company and KUFPEC.
The launch supports Cairo’s push to lift domestic gas output through greater investment, exploration and field development. The government is targeting roughly 4.2 billion cubic feet per day by the end of the 2026–2027 fiscal year, a drive meant to close the gap between local supply and rising demand and cut dependence on imported gas.
Shell Egypt and Kuwait Foreign Petroleum Exploration Company (KUFPEC) said Sunday that output began just three years after the discovery.
The field sits within the North East El Amriya concession in the Mediterranean Sea. Shell controls 60% of the project, and KUFPEC’s Egyptian subsidiary holds the other 40%.
The partners signed off on development in June 2025. A newly built seven-kilometer (4.34-mile) pipeline ties the field into the existing West Delta Deep Marine infrastructure, which sends the gas to the Burullus processing facility before it reaches Egypt’s national grid. Shell said relying on existing facilities sped up the timeline.
“Bringing Mina West into production just three years after discovery demonstrates what we can achieve when we work towards a shared goal from the outset,” said Dalia Elgabry, Shell Egypt’s vice president and country chair.
Elgabry attributed the fast turnaround to early coordination among Egypt’s Petroleum Ministry, the Egyptian Natural Gas Holding Company and KUFPEC.
The launch supports Cairo’s push to lift domestic gas output through greater investment, exploration and field development. The government is targeting roughly 4.2 billion cubic feet per day by the end of the 2026–2027 fiscal year, a drive meant to close the gap between local supply and rising demand and cut dependence on imported gas.
Legal Disclaimer:
MENAFN provides the
information “as is” without warranty of any kind. We do not accept any
responsibility or liability for the accuracy, content, images, videos,
licenses, completeness, legality, or reliability of the information
contained in this article. If you have any complaints or copyright issues
related to this article, kindly contact the provider above.

Comments
No comment