Tuesday, 02 January 2024 12:17 GMT

Eneva Trades Coal For Full Control Of A Pecem Asset


(MENAFN- The Rio Times) Brazil · ENERGY

Key Facts

    - The deal Eneva and Diamante signed a share swap on the evening of 1 September 2026. - What Eneva gives All of Itaqui Geração de Energia, which owns the 360 MW coal plant at Porto do Itaqui. - What Eneva gets Diamante's 50% of Porto do Pecém Transportadora de Minérios, plus cash. - The cash A balancing payment of 400 million reais (US$77.6 million), with up to 467 million more if a contract starts early. - Why Eneva ends up sole owner of the vehicle that will help build a liquefied gas terminal at Pecém. - Still pending The swap needs clearance from the competition regulator Cade and has no published closing date.

Eneva is not selling its last coal plant. It is trading it, for a stake in a gas terminal and a cheque.

RTAsk Rio TimesLatin American markets, currencies and companies full Ask Rio Times → Open the full Ask Rio Times → RTAsk Rio TimesLatin American markets, currencies and companies a question, or type your own - the answer appears right here the full Ask Rio Times →

Eneva has agreed to hand its last coal-fired power plant to Diamante. In return it takes full ownership of a transport company at the Pecém industrial complex, plus cash.

The contract was signed on the evening of 1 September 2026 and announced the next morning. It is legally a swap, not a sale.

What Each Side Hands Over

Eneva transfers all the shares of Itaqui Geração de Energia. That company owns the coal-fired Porto do Itaqui plant, rated at 360 megawatts.

Diamante transfers its 50% of Porto do Pecém Transportadora de Minérios, known as PPTM. Eneva already held the other half and becomes sole owner.

The counterparty is Diamante Geração de Energia and its affiliates. Diamante is a vehicle created by the asset manager FRAM Capital.

Diamante bought Eneva's other coal plant, Pecém II, in a deal that closed on 31 August 2026. It also owns Pecém I outright, and the Jorge Lacerda complex in Santa Catarina.

The Cash, and What Triggers More of It

Because the two sides of a swap are rarely worth the same, Diamante pays Eneva a balancing amount. Brazilian law calls this a torna.

That payment is 400 million reais (US$77.6 million) in nominal terms. It is adjusted for inflation from a base date of 30 June 2026 to closing, plus other adjustments.

A further 467 million reais (US$90.6 million) is contingent. It becomes payable only if the supply period of Itaqui's capacity contract is brought forward.

The two figures together come to 867 million reais. But that is only the cash leg, because no value was disclosed for the PPTM stake.

Live Company IntelligenceEneva S.A - the full investor dossierInside: live share price, market cap, three-year financials, valuation, ESG and peer benchmarks - plus the latest Rio Times coverage. E ◆ Live Company Intelligence Eneva SA: ENEV3ENEV3UtilitiesUtilities – Diversified2,054 employees R$50.93B Market cap Valuation & profitability Market capR$50.93B Revenue (TTM)R$19.14B P / E ratio53.0 Profit margin5.0% Return on equity7.2% Price & risk 52-wk low
$14.89 52-wk high
$28.12 Beta (volatility)0.31 200-day average$23.68 Revenue trend · 6y 20202025 Latest R$18.42B Ownership Institutions75.2% Shares outstanding1.92B Dividend No regular dividend - earnings reinvested for growth. What Eneva does. Eneva S.A., an integrated energy company, engages in the exploration, production, and commercialization of natural gas and liquids in Brazil. The company generates electricity through natural gas, steam, coal, and solar energy. It also supplies natural gas solutions to the on-grid and off-grid market for thermal power plants, pipeline operators, and industrial... Data: RT fundamentals (ENEV3) · figures in BRL · as of 2 Sep 2026More company intelligence → Why Eneva Wants PPTM

PPTM is a pipeline transport company registered at the Pecém complex in Ceará. It has served the coal plants there, which is why it was owned half each by their two owners.

Eneva's filing describes it looking forward rather than back. PPTM, it says, will form part of building a terminal to import, store and regasify liquefied natural gas.

That terminal is designed to move up to 14 million cubic metres of gas a day. Owning the transport company outright removes a partner from a project Eneva wants to control.

The End of Coal, When It Closes

Eneva held exactly two coal plants, Itaqui and Pecém II. Pecém II went to Diamante on 31 August, and Itaqui is the last one.

The exit is not complete yet. Closing depends on conditions including clearance from Cade, Brazil's competition regulator.

No closing date has been published. Eneva's filing does not name any other regulator whose approval is required.

Leaving coal is not the same as leaving fossil fuels. Eneva keeps a large gas fleet in the Parnaíba basin and a 331 megawatt fuel-oil plant in Maranhão.

The Contracts That Come With the Plant

Itaqui sells power under regulated contracts that run to 21 December 2027. It also won a ten-year capacity contract in an auction held on 18 March 2026.

That contract runs from 1 August 2031 and covers 311.7 megawatts, at fixed annual revenue of about 503.6 million reais. It is the start date of this contract that the contingent payment turns on.

Where Eneva Stands

Eneva carried net debt of 19.8 billion reais at 30 June 2026, or 3.2 times earnings. That is up from 2.8 times in March.

Second-quarter net income was 31.2 million reais, down more than 90% on the year, though operating cash flow set a record. The company is worth about 51 billion reais.

The shares have risen roughly a third in 2026. Bradesco BBI advised Eneva on the swap.

Frequently Asked Questions Is this a sale?

No. The contract is legally a swap, a permuta under article 533 of Brazil's civil code, with cash on top.

What does Eneva get for its coal plant?

Diamante's 50% stake in the Pecém transport company, plus 400 million reais in cash. A further 467 million follows if a capacity contract starts early.

Does this end Eneva's use of coal?

It will, once the deal closes. Itaqui is the last of the two coal plants Eneva held, the other having gone to the same buyer in August.

What is PPTM?

Porto do Pecém Transportadora de Minérios, a pipeline transport company at the Pecém industrial complex in Ceará. Eneva says it will form part of building a liquefied natural gas terminal there.

When does it close?

No date has been published. Closing depends on conditions including clearance from Cade, Brazil's competition regulator.

Connected Coverage

    Brazil's slowing industry The OceanPact and CBO merger

Sources: Eneva fato relevante of 2 September 2026 filed with the CVM; Eneva fato relevante of 18 March 2026 on the capacity auction; Eneva second-quarter 2026 results; Reuters via InfoMoney; Money Times; ANEEL. Converted at 5.1570 reais to the dollar, the Banco Central PTAX selling rate for 1 September 2026.

This article was drafted with automated assistance and reviewed before publication. How we use AI · Report an error

In depth

    Brazil inflation, Selic and rates 2026

Read More from The Rio Times

    Pix Is About to Pass Cards at Brazil's Checkout Brazil's T4F Leaves the Stock Exchange for R$12 Million Brazil's PagBank Guides to a Smaller Dividend, Not a Bigger One

MENAFN02092026000070016031ID1111614764



The Rio Times

Legal Disclaimer:
MENAFN provides the information “as is” without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the provider above.



More Story