Alurion Launches Amargosa PFS Program To Advance A Scalable Atlantic-Basin Bauxite Project
| Amargosa Infill Drilling Program - Scope | |||
| Program | Holes | Metres | Analytical suite |
| Auger drilling - Central District | 203 | 2,436 | Total Available Alumina (TAA), Reactive Silica (RSI) and Total Organic Carbon (TOC) |
| Diamond drilling - Central District | 20 | 800 | TAA, RSI, TOC, XRF, ICP-MS |
| Total | 223 | 3,236 | ~3,600 samples |
Program scope is indicative and subject to change as drilling progresses and results are received
Sampling, analysis and quality control
Samples will be collected at nominal one-metre intervals, logged and dispatched to SGS laboratory in Minas Gerais, Brazil. Auger samples will be assayed for TAA, RSI and total organic carbon. Diamond core will additionally be analysed by XRF and ICP-MS to characterise gallium and the critical mineral suite associated with the beneficiable bauxite. Certified reference materials, blanks and duplicates will be inserted throughout, consistent with the QA/QC protocols applied to the existing Mineral Resource database.

Figure 1: First Alurion diamond drill hole in Lapa target, in Central District – Amargosa Project

Figure 2: Amargosa 2026 infill drilling campaign. Central District collar plan, auger and diamond collars planned for the 2026 campaign, shown against the historical Rio Tinto auger, air-core and the direct-ship-bauxite pit outlines
Trenching and Bulk-Samples: Testing Yield, Quality and Co-Product Potential
Up to 16 trenches across the Central and North Districts will generate representative bulk samples of Amargosa's DSB and beneficiable bauxite. The sample scale allows Alurion to test product performance, processing yield and potential co-products under conditions that drilling alone cannot replicate.
Historical Rio Tinto metallurgical test work provides a compelling basis for the program. Twenty-two bulk composites of approximately eight tonnes each were screened at natural moisture using industrial-scale equipment. The historical tests recovered 43%-49% of feed mass into a +22 mm product meeting the target 40% TAA and less than 3% RSI specification.
That recovery was achieved at a substantially coarser cut than the +0.85 mm (20 mesh) cut underpinning Alurion's Mineral Resource Estimate's with a 40.7% beneficiation-yield benchmark. Alurion will test whether this higher yield performance can be sustained, or improved, using representative bulk samples and a controlled bauxite processing flowsheet.
What the program is designed to establish
- More saleable product: Test potential beneficiation-yield improvement across the 470Mt beneficiable-bauxite Mineral Resource Potential new product value streams: Assess recovery of ilmenite, zircon and monazite co-products from material currently reporting to fines An export-ready product: Confirm particle sizing, assess whether crushing is required, moisture optimisation and establish safe-shipping parameters through Transportable Moisture Limit (TML) testing Value to alumina refiners: Undertake Bayer-process trials to quantify digestion conditions, alumina recovery, caustic consumption, residue generation and gallium deportment
The results will provide important inputs for product qualification, customer offtake negotiations and the Amargosa PFS and test not only how much saleable bauxite could be recovered, but also how efficiently it could be processed, transported and refined.

Figure 3: Alurion's first trench operation in Lapa target, site AMBX1951, Central District, Amargosa Project

Figure 4: Bulk sample test work program
Logistics growth and scalability
Near-Term Base Case: Unlocking High-Capacity Road Haulage
Alurion has commissioned a comprehensive, independent road-logistics study for the Amargosa project. The study is designed to evaluate road haulage parameters for the PFS and the scope for significant, staged capacity expansions via road haulage to support future production upside. It will establish robust parameters for a highly scalable transport network, focusing on:
- Route Optimisation: Maximising efficiencies along the highway network to Enseada and the secondary route that connects to a potential FIOL rail load-out High-Volume Fleet Configurations: Establishing optimal vehicle specifications to support bulk tonnage operations in a safe, reliable and flexible manner, and minimise operating costs Staged Capacity Expansion: Developing phased logistics models that allow transport capacity to grow in tandem with potential production increases
Medium-Term Case: Large-capacity FIOL rail + Porto Sul infrastructure
While scalable road transport underpins a robust initial development case, the potential southern rail-port export chain offers Alurion a medium-term pathway to prospective larger-scale bauxite export volumes. Connecting road haulage to a FIOL rail load-out for export through the planned Porto Sul terminal provides strategic optionality to pursue larger-scale export volumes over time.
Strategic Market Opportunity and Early Commercial Engagement
China import demand is accelerating beyond previous forecasts
China's reliance on imported bauxite continues to accelerate. China imported 140 Mt during the seven months to 31 July 2026, 13.5% above the prior corresponding period and almost equal to the approximately 141 Mt imported in the whole of 2023. The seven-month volume annualises to approximately 240 Mtpa, more than 2.2 times 2021 imports, indicating that China's bauxite import requirement is advancing fast.
The annualised figure is a simple run-rate, not a forecast, and may be affected by seasonality, shipment timing and inventory movements.
Supply concentration strengthens the case for supply diversification
China sourced 113 Mt of bauxite from Guinea during January–July 2026, nearly 81% of its total bauxite imports and almost 30 percentage points above Guinea's 51% share in 2021.
Guinea now supplies approximately four out of every five tonnes of bauxite imported by China. By comparison, Australia supplied approximately three out of every five tonnes of China's iron-ore imports in 2025, with Brazil contributing approximately one further tonne in five. At the single-country level, this is materially more concentrated than its iron-ore supply.
In Alurion's view, the combination of rapidly increasing import reliance and high geographic concentration strengthens the strategic rationale for alumina producers to develop new bauxite supply options that complement Guinea and diversify country, policy, infrastructure and logistics exposure.
A Scalable, Independent Atlantic-Basin Supply Opportunity
Amargosa combines scale with a practical initial road-led development pathway and potential longer-term access to the high-capacity FIOL–Porto Sul export infrastructure corridor. This staged logistics strategy allows Alurion an initial route to market while preserving significant future expansion optionality. Amargosa is strategically positioned as a prospective large-scale, independent Atlantic-basin source of bauxite, subject to successful studies, approvals, infrastructure, financing and development.
Early commercial engagement
Within weeks of Alurion's spin-out, the Company received inbound interest and commenced preliminary, non-binding engagement with alumina and aluminium groups from China, Middle East and Brazil.
Discussions are centred around exploring product qualification, potential offtake and partnerships. The early timing of this engagement provides an opportunity to align Amargosa's technical programs with prospective customer requirements. The discussions remain preliminary and exploratory. Amargosa's development remains subject to successful technical and economic studies, permitting, financing and development.
Sources: Shanghai Metals Market, China Customs data for January–July 2026; 2025 China Customs iron-ore data; Annualised figures and percentage comparisons are calculations by Alurion
Path to mid-2027 PFS
The drilling, trenching, product, metallurgical and logistics programs are sequenced to deliver the principal technical inputs required for the Amargosa PFS targeted for mid-2027.
| Indicative Program Timetable | |
| Technical Activity | Indicative timing |
| Infill auger drilling - Central District | Q4 2026 |
| Diamond drilling - Central District | Q4 2026 |
| Trenching and bulk sampling program | Q4 2026 |
| Ore characterisation, moisture, TML and Particle Size Distribution test work | Q1 2027 |
| Critical mineral co-product recovery results | Q2 2027 |
| Updated JORC Mineral Resource Estimate: Direct-ship-bauxite | Q2 2027 |
| Updated JORC Mineral Resource Estimate: Beneficiable bauxite and critical mineral estimate | Q2 2027 |
| Pre-Feasibility Study: Amargosa Direct-ship-bauxite | Mid-2027 |
The above timetable is indicative only and subject to change.
Authorisation
This announcement has been authorised for release by the Chief Executive Officer.
For further information and enquiries please contact:
Maurício Noronha
Chief Executive Officer
Alurion Resources Limited
...
Cautionary Statement - Scoping Study
References in this announcement to the Amargosa Scoping Study are references to the Amargosa Scoping Study as set out in the Independent Technical Assessment Report (ITAR) in Alurion's Prospectus dated 5 June 2026 and the Supplemental Prospectus dated 19 June 2026. The Scoping Study is a preliminary technical and economic assessment prepared to an intended accuracy of ±35% and is based on low level technical and economic assessments that are insufficient to support the estimation of Ore Reserves. The Production Target evaluated in that study comprises approximately 89% Indicated Mineral Resources and 11% Inferred Mineral Resources. Inferred Mineral Resources are considered too speculative geologically to apply Modifying Factors in sufficient detail to support the estimation of Ore Reserves, and there is no certainty that the Production Target, or the forecast economic outcomes derived from it, will be realised. Investors should not make investment decisions based solely on the results of the Scoping Study.
The programs described in this announcement are exploration, metallurgical and study activities. No Ore Reserve has been estimated for Amargosa, and no assurance can be given that the drilling, trenching or test work programs will achieve the objectives described, that Mineral Resources will be upgraded to higher confidence categories, that improved beneficiation yields or critical mineral recoveries will be demonstrated, or that a Definitive Feasibility Study will support development of the Project. Development of the Project, if it proceeds, will require additional funding, and there is no certainty that such funding will be available when required or on acceptable terms.
Forward-Looking Statements and Information
This Announcement may contain“forward-looking statements” and“forward-looking information”, including statements and forecasts which include (without limitation) expectations regarding industry growth and other trend projections, forward-looking statements about the Amargosa Project, future strategies, results and outlook of ALU and the opportunities available to ALU. Often, but not always, forward-looking information can be identified by the use of words such as“plans”,“expects”,“is expected”,“is expecting”,“budget”,“outlook”,“scheduled”,“target”,“estimates”,“forecasts”,“intends”,“anticipates”, or“believes”, or variations (including negative variations) of such words and phrases, or state that certain actions, events or results“may”,“could”,“would”,“might”, or“will” be taken, occur or be achieved. Such information is based on assumptions and judgments of ALU regarding future events and results. Readers are cautioned that forward-looking information involves known and unknown risks, uncertainties and other factors which may cause the actual results, targets, performance or achievements of ALU to be materially different from any future results, targets, performance or achievements expressed or implied by the forward-looking information.
Forward-looking statements are not guarantees of future performance and involve known and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond the control of the Company, the Directors and management of the Company. These and other factors could cause actual results to differ materially from those expressed in any forward-looking statements.
Forward-looking information and statements are (further to the above) based on the reasonable assumptions, estimates, analysis and opinions of ALU made in light of its perception of trends, current conditions and expected developments, as well as other factors that ALU believes to be relevant and reasonable in the circumstances at the date such statements are made, but which may prove to be incorrect. Although ALU believes that the assumptions and expectations reflected in such forward-looking statements and information (including as described in this Announcement) are reasonable, readers are cautioned that this is not exhaustive of all factors which may impact on the forward-looking information.
The Company cannot and does not give assurances that the results, performance or achievements expressed or implied in the forward-looking information or statements detailed in this Announcement will occur and prospective investors are cautioned not to place undue reliance on these forward-looking information or statements.
Competent Persons Statement
The information in this announcement that relates to the Amargosa Mineral Resource Estimate and the Amargosa Scoping Study is extracted from the Independent Technical Assessment Report (ITAR) in Alurion's Prospectus dated 5 June 2026 and the Supplemental Prospectus dated 19 June 2026 (“Prospectus Reports”), which are available to view at Alurion confirms that: (a) it is not aware of any new information or data that materially affects the information included in the Prospectus Reports; (b) all material assumptions and technical parameters underpinning the Mineral Resource Estimate and the Production Target, and the forecast financial information derived from the Production Target, in the Prospectus Reports continue to apply and have not materially changed; and (c) the form and context in which the relevant Competent Persons' findings are presented in this announcement have not been materially changed from the Prospectus Reports. No new Exploration Results, Mineral Resources or Ore Reserves are reported in this announcement.
All photos accompanying this announcement are available at:

Legal Disclaimer:
MENAFN provides the
information “as is” without warranty of any kind. We do not accept any
responsibility or liability for the accuracy, content, images, videos,
licenses, completeness, legality, or reliability of the information
contained in this article. If you have any complaints or copyright issues
related to this article, kindly contact the provider above.

Comments
No comment