Two Main Power Lines Restored In Kharkiv


(MENAFN- UkrinForm) Ukraine's power system operator NEC Ukrenergo has fully restored operations at two main power lines in Kharkiv following a Russian strike on local critical infrastructure that left the area de-energized.

That's according to Volodymyr Kudrytskyi, Ukrenergo Chairman of the Board, who spoke at a briefing hosted by media Center Ukraine – Ukrinform on Wednesday, September 14.

'We managed to restore two main transmission lines providing power in Kharkiv,' said the Ukrenergo chief.

He noted that the company's specialists, together with Kharkivoblenergo emergency repair teams, continue to work on restoring power supplies to the remaining part of the area affected by blackout due to the Russian missile strike on September 11.

Read also: Power supplies fully severed in two Ukrainian regions after Russia hits critical infrastructure

Kudrytskyi emphasized that within 4.5 hours, the emergency team restored 85% of energy supply in all de-energized areas.

He also informed that Ukrenergo is preparing for any war scenarios, including by readying backup power schemes, emergency stocks of materials, and response teams.

As reported, as a result of massive Russian strikes on September 11, a total of 40 substations of various voltages were de-energized; four employees of energy companies were killed. Residents of Kharkiv, Donetsk, Zaporizhia, Dnipropetrovsk, and Sumy regions were left without power supplies.

MENAFN14092022000193011044ID1104865764


UkrinForm

Legal Disclaimer:
MENAFN provides the information “as is” without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the provider above.