Kyrgyzstan Shares Progress On Karakul Small HPP Dev't
According to the information, as of today, earthworks for the preparation of the 110 kV open distribution device (ODD) area have been completed, along with the grounding of the substation.
The following construction stages have also been completed:
- Construction and installation works for the main water intake unit;
- Active construction of the HPP building is currently ongoing, with concreting of levels I-IV completed up to a height of 727.9 meters;
- Installation of the pressure pipeline has been finished.
This month, construction work on the station building is expected to continue.
The plant's planned capacity is 18 MW, with an annual average power output of 110 million kWh, which will provide electricity to approximately 3,600 homes in the region (averaging 5 kWh per house). The construction is expected to be completed in the first half of 2026.
The project's investor and general contractor is the Zhagalmai company. An investment agreement for the construction of the small HPP was signed on June 16, 2023, between Karakul HPP and Zhagalmai.

Legal Disclaimer:
MENAFN provides the
information “as is” without warranty of any kind. We do not accept
any responsibility or liability for the accuracy, content, images,
videos, licenses, completeness, legality, or reliability of the information
contained in this article. If you have any complaints or copyright
issues related to this article, kindly contact the provider above.
Comments
No comment