Completion of pipeline laying in first platform of SP field Phase 11 in Persian Gulf


(MENAFN) Pars Oil and Gas Company (POGC) which is in command of developing the field declared that the subsea pipe laying action of the energy spread line from the first platform of South Pars phase 11 in the Persian Gulf to the onshore refinery has been established.

As mentioned by the POGC portal report, the pipe laying action of the gas transmission line from Platform 11B which began on July 28 was finished on Friday, August 12.

This process included connecting a 32-inch subsea pipeline for spreading sour gas and a 4.5-inch mono-ethylene glycol injection pipeline both with an approximate length of 15 kilometers. The pipelines are linked to the offshore pipeline of platform 12C from South Pars phase 12 to carry sour gas from platform 11B to the stated phase’s refinery on land.

The pipeline is built with the target of transporting 28 million cubic meters of gas outputted at South Pars platform 11B to the onshore phase 12 refinery in Pars 2 Kangan district.

MENAFN14082022000045014228ID1104693459


Legal Disclaimer:
MENAFN provides the information “as is” without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the provider above.